Darlington Road Pavement Rehabilitation Project

HomeNews

Darlington Road Pavement Rehabilitation Project

May 28, 2020 By: Staff Report ~~Construction work begins the week of June 1, 2020~~ HOLIDAY, FL  ----  The Darlington Road Pavemen

Michigan Man, 2 From Georgia Died From Drowning Saturday In Florida Gulf
New Port Richey Man Struck And Killed By Hit-And-Run-Driver In Spring Hill
St. Pete Police Looking For Armed Robbery Suspect Who Fired His Gun

May 28, 2020

By: Staff Report

~~Construction work begins the week of June 1, 2020~~

HOLIDAY, FL  —-  The Darlington Road Pavement Rehabilitation Project is scheduled to begin the week of June 1, 2020.  The road work will include milling and resurfacing of the existing roads, as well as new pavement markings and restriping.

The paving project includes both the east and westbound lanes of Darlington Road, from U.S. 19 to the intersection of Arcadia Road.

Project Details:

  • Work hours are Monday through Friday, 9 a.m. to 4 p.m.
  • Expect single lane closures with message boards directing traffic.
  • Project is expected to take eight workdays, depending upon weather conditions.
  • Target completion date is June 11, 2020.

Ajax Paving Industries of Florida, LLC is the contractor for this Pasco County Department of Public Works project.